Case Studies

EPCM Case Studies: Real Projects, Real Numbers

Client names are confidential which is their call, not ours. But the engineering problems, the project numbers, and the outcomes are real. If you recognise a project, you probably know the client too.

We add projects as they complete and our clients give permission to share. These represent our most recent work.

Pharmaceutical

Effluent & Solid Waste Treatment: Global Pharma Manufacturer, North Brabant

A major pharmaceutical manufacturer operating BSL2 and BSL3 containment facilities needed engineered waste treatment across two streams: liquid effluent and solid biological waste. We acted as Engineering Project Leader across both programmes from process design through to commissioning.

Three separate Effluent Treatment Plants were designed and commissioned to handle slurry-bearing waste from high-containment areas, each engineered for full decontamination to regulatory disposal standards and not dilution. Alongside this, we delivered multiple autoclave units across both containment classes and commissioned the first shredder-autoclave combination unit ever installed at a pharmaceutical manufacturing site.

Key Numbers
€17M combined project value
3 ETPs commissioned across BSL2/BSL3 boundaries
First shredder-autoclave installation at a pharmaceutical plant
100% regulatory decontamination compliance on commissioning sign-off
EngineeringBSL3 / BSL2BiocontainmentAutoclaveETP
Read full case study →
Food & Beverage

UHT Processing & Aseptic Packaging: Dairy Cooperative, Gelderland

New UHT processing and aseptic packaging line inside an operating dairy factory. The non-negotiable: install everything without shutting down existing production and pass FSSC 22000 certification before the first commercial product run. We redesigned the CIP routing to enable phased commissioning, ran a shadow HACCP validation alongside construction, and managed 14 contractors simultaneously on a site that never stopped producing.

Key Numbers
€12.2M project value
Zero unplanned production stoppages during 9-month construction
FSSC 22000 surveillance audit passed first time
18% energy reduction vs. old line (heat recovery integration)
Delivered €340K under budget (procurement savings passed to client)
Full EPCMHACCPCIP/SIPEHEDG2023
Read full case study →
Industrial & Manufacturing

Factory Expansion & Equipment Procurement: Specialty Materials Manufacturer, Noord-Brabant

A high-tech manufacturer of engineered carbon components needed to expand production capacity while partially rebuilding an operational section of the factory. We were engaged as Owner's Project Manager, representing the client's interests across the full scope: structural works, a complete MEP installation, and procurement and commissioning of multiple precision machining systems for carbon disc processing.

The challenge was running the expansion without halting production in adjacent areas. We managed construction sequencing, supplier tendering, and equipment interfaces, keeping the client in full contractual control of every appointment throughout.

Key Numbers
€15M project value
Full MEP scope across expanded and rebuilt areas
Multiple precision machining systems procured and commissioned
Brownfield expansion — zero unplanned production interruptions
Owner's PMMEPEquipment ProcurementBrownfield
Industrial & Manufacturing

Cleanroom Gas Distribution System: Semiconductor Equipment OEM, Eindhoven

A world-leading semiconductor equipment manufacturer required a complete new high-purity gas distribution network inside an operational cleanroom facility. We took responsibility for the full design and build including pipe routing developed in close coordination with the owner's engineering team, specification of high-purity fittings, and a full off-site prefabrication programme before controlled installation in the cleanroom environment.

Prefabrication was non-negotiable: cutting or welding inside the cleanroom was not an option. Every pipe assembly had to be designed, fabricated, tested, and certified before entering the controlled zone. We managed the design review cycle with the owner, the fabrication shop, and the on-site installation team simultaneously.

Key Numbers
€30M project value
High-purity gas distribution across live cleanroom boundary
Zero in-cleanroom fabrication — full off-site prefabrication certified before site entry
Owner design review cycle completed to programme. No rework required post-review
Project ManagementCleanroomHigh-Purity GasPrefabricationSemiconductor
Portfolio Summary

The numbers across all projects.

€140M+
Total project value managed
100%
First-time audit pass rate
0
Critical regulatory findings
15+
Years on the client side

Have a project that looks like one of these? Let's talk.

Get in touch