Open Actions
GEA
Revised steel delivery schedule — confirm by 12 May
C2
Issue concrete pour permit to work — due 10 May
CLIENT
Approve CIP circuit changes — FAT protocol on hold pending this
Risk Register — Open Items
HIGH
Concrete pour weather window — 3-day risk to programme
MED
Electrical panel lead time — 12 wks, order not yet placed
LOW
CIP validation scope change — cost impact being assessed